State Technical Supervision, clean-up day and production
The process of preparing for obtaining the certificate of construction completion is gaining momentum.
At the end of last week, representatives of the State Technical Supervision Service worked at the construction site of the "Sovelmash" design and engineering technology department. They inspected the readiness of electrical equipment to connect the facility to a permanent power supply. A report has been compiled with comments to be addressed within a week, after which the inspection will be carried out again.
Installation of the cooling system for the building is in progress. The second room of the cooling plant is being fitted with equipment.
The offices of the D&E employees are getting their "name plates". The metal door signs have been made by "Sovelmash".
The "Sovelmash" D&E equipment has been used to manufacture in-house developed products:
• stators for the quadcopter propellers,
• semi-finished covers for water-cooled motors,
• blanks for the quadcopter frame.
On April 20, a centralised clean-up day was held at the "Alabushevo" site of the special economic zone "Technopolis "Moscow". Four labourers of the contractor were cleaning the premises of "Sovelmash". The D&E premises had been put in order even before the clean-up day.