Day 28: comments from A. Sudarev about the "Sovelmash" D&E construction
5 July 2021
In this video, you will see the changes that have taken place over the weekend, as well as learn about the new types of work.
Alexander Sudarev, head of the information and analytics department, will tell you in detail about the "Sovelmash" D3333E construction.
Work continues on the construction of staircases, reinforcement and concrete work is in progress.
The edging necessary for the formation of ceilings has been made on the metal structures, the profiled sheets are being installed too, after which the concrete will be poured.
Alexander tells about the roofing for the roof, metal structures, their alignment, slabs for the basement floor and much more.