Week results in the project "Duyunov's motors"
What searching for a plant to produce Duyunov's motors has ended with and when the documentation for the innovative centre construction will be submitted to the state expert review?
We are summing up the week results in the project "Duyunov's motors" and sharing what tasks the team has managed to complete for this period of time.
We have found an enterprise that can be used for launching the production of the first batch of combined winding motors based on standard motors. Now the work on organizing the check of these motors is being done. It's necessary to deliver the pilot models of these motors to the "SovElMash" laboratory and mount the "Slavyanka" type winding on them and then hold the tests. In case the results are positive, the first batch of Duyunov's motors will be manufactured and sent to the company's licensees for sale. According to the preliminary forecast, it can take place in the 1st quarter of 2020.
Meanwhile, the team responsible for the construction of the "SovElMash" innovative centre in "Technopolis "Moscow" are putting all of their efforts into making up for the delay in the construction times that took place at the previous stages. There are no more new delays.
Preparing the metal framework required for the building construction is underway.
On December 23, all construction documentation is planned to be submitted for the state expert review.
In the course of the passing week, the company SOLARGROUP shared good news with the investors. The hard copies of all documents dealing with purchasing investment shares have become available. You can request the papers in the back office. The details were provided here - /news/posts/v-licnom-kabinete-dostupen-zakaz-dokumentov-investora-1031
By summing up the weekly results we - the team of the project "Duyunov's motors" - can see the development and it inspires us to continue working.